PROPERTIES UNDER CONTRACT

These Central Indiana properties are currently Under Contract as we prepare them for the next stage of transformation. Each home here is a revitalization opportunity, moving one step closer to becoming the safe, well-maintained housing our community deserves. Follow our social media channels to see the "After" photos very soon!

20250708_132649_edited.jpg

Week 1

We’re making key foundational updates, from systems to structure, and setting the stage for what’s to come. It’s still early, but progress is moving steadily behind the scenes, including some important upgrades that will make a huge difference later on.

20250708_132649_edited.jpg

Week 2

This week, we've been focused on tackling some of the bigger pieces of the puzzle. It's exciting to see the vision start to take shape, even in these early stages. We’re putting in the work and seeing the rewards, little by little.

20250708_132649_edited.jpg

Week 3

It's incredibly exciting to see the vision really start to take shape, even in these early stages. We're putting in the work, and seeing the rewards little by little! keep you updated as we transform this property.

20250708_132649_edited.jpg

Week 4

The upstairs drywall is almost fully done, giving the space a fresh new feel. The new insulation is now in place, setting us up for better energy efficiency and comfort. And the big win, the sewer line replacement is officially complete!

20250708_132649_edited.jpg

Week 5

We’re getting close to the finishing touches on this beautiful home. All the sheetrock is up, layout updates are complete, and it’s shaping up perfectly.

20250708_132649_edited.jpg

Week 6

 The new HVAC and furnace are fully installed for ideal heating and cooling, and a fresh coat of primer is on the walls, creating a clean slate for the next phase. We're now moving on to the final stages of this project: finishing paint, new flooring, cabinets, and fixtures.

20250708_132649_edited.jpg

Week 7

This week is all about big progress. We're so excited to be getting the flooring done, and the holes are already cut for our new light fixtures. 

20250708_132649_edited.jpg

Week 8

We’re getting closer to the final stretch! Trim work, painting touch ups, and last minute details are all coming together. Every room is starting to feel complete, and the overall transformation is really taking shape.

20250708_132649_edited.jpg

Week 10

We’re making great strides as the project nears completion. It’s been exciting to watch everything evolve from the ground up, and we’re almost there.

20250708_132649_edited.jpg

Week 12

Big progress this week! The flooring is nearly finished, electrical and lighting are all set, kitchen cabinets and counters are almost done, and the vintage-style trim is in place and stained. On track to wrap things up in the next week or two! Stay tuned!

20250708_132649_edited.jpg

Week 14

Fresh photos are coming in! The downstairs bathroom tile is officially done and the upstairs bathroom is almost complete. We’re down to the finishing touches and expect to wrap everything up in about a week. Can’t wait to show the final look!

20250708_132649_edited.jpg

Week 15

The front porch, garage floor, and sidewalk have all been completely redone, the interior’s nearly finished, and the exterior’s looking fresh and newly seeded Just a small punch list left before this beauty hits the rental market!